Site Survey: | MAY 25 - 04 JUN 1950 site survey - pdf |
Construction Date: | 1951 - 1952 |
Constructed by: | ENS Norman J. Glover - Construction Engineer - 1999 Interview - pdf The interview was by Joe Stevens on September 2, 1999 located at http://kadiak.org/spruce_cape/index.html |
Established: Commissioned: |
FEB 1952 |
Disestablished: | JAN 1980 |
Operated by: |
USCG |
Station Unit Identifier: | |
Mail address: | 1956: Box 41, Navy 127, c/o P.M. Seattle, WA |
Station Project code name: |
|
Station AKA: | KODIAK |
Personnel Allowance: | JAN 1953 - 1 Officer; 13 Enlisted 1955 - 1 Officer, 11 Enlisted |
Station Mascot: | |
Miscellaneous: | 1952 - Station to be an 18 month tour restricted 1956 - On commercial power; two gasoline standby generators 1956 - Non-restricted duty - 18 month tour 29 MAR 1964 - Station off-air for 36 minutes following the earthquake on 28 MAR 1964 |
Commanding Officers/Officer in Charge: | Commanding Officers: 1952 - 1953 LT Herbert J. Lynch (JAN - JUL) 1953 - 1954 1954 - 1955 LTJG Sidney B. Vaughn (JUN - DEC) 1955 - 1956 1956 - 1957 LTJG William E. Smith (? - JUN) 1957 - 1958 LTJG Clyde T. Lusk (JUN - ?) 1958 - 1959 1959 - 1960 1960 - 1962 LTJG Robert L. DeHichiell 1962 - 1963 1963 - 1964 1964 - 1965 LTJG Keith 1965 - 1966 1966 - 1967 LTJG Gill R. Goodman 1967 - 1968 LTJG Donald G. Campbell 1968 - 1969 Officer in Charge: 1969 - 1972 ETC Paul Richardson 1972 - 1973 ETC Cobb 1973 - 1974 ETC Evert Clark 1974 - 1975 ETC Donald T. Stavton (? - SEP) 1975 - 1976 ETC Lawrence Gemoets (SEP - MAR) 1976 - 1978 ETC Roger Johnson (MAR - JUN) 1978 - 1980 ETC Harvard K. Madigan (JUN - JAN) DECOMM |
Chain: | GULF OF ALASKA |
Station Letter designation: | "K" |
Radio Call Sign: | NMJ- |
Declared Operational date: | 11 MAR 1952 |
Operations Ceased: | 312400Z DEC 1979 |
Station Operation: | Single SLAVE/SECONDARY (SS) |
Station pair: Loran rate: Coding delay: Baseline: |
SPRUCE CAPE (S) - OCEAN CAPE (M) 1L3; 1L7 1000 us Approx. 405.5 Nautical miles |
On-air testing date: | 1L3; 01 MAR 1952 |
On-Air: | 1L3; 11 MAR 1952 1L7; MAY 1961 |
Off-Air: | 1L3; MAY 1961 Change of rate 1L7; 243100Z DEC 1979 Termination of service |
Monitor Rate: | Cross rate monitoring |
Equipment: | 1951 - UE-1 Timers; T-137 Transmitters; T-138 Amplifiers APR 1957 - AN/FPN-30 Timers; T-325 Transmitters; AM-1700 Amplifiers |
Radiator: | 1952 - "T" 1964 - 129ft tower |
c,/1952
(courtesy of the U.S.C.G.)
(courtesy of the U.S.C.G.)
(courtesy of the U.S.C.G.)
Year unknown