LORAN STATION BOISE CITY
36 30 20.783 N 102 53 59.487 W
Fact Sheet
Site Survey: | |
Construction Date | 1990 |
Constructed by: | |
Established: | PreCom established July 1st 1990 Placed in service Nov 8th 1990 |
Disestablished: | FEB 2010 |
Operated by: | USCG |
Chain: | 8970 – GREAT LAKES 9610 – US SOUTH CENTRAL |
Station Letter designation: | 8970 – “Z” 9610 – “M” |
Station code name: | |
Station Unit Number: | |
Station nickname: | |
On-air testing date: | 9610M - Aug 1990 – Dec 24th 1990. 8970Z – Aug 1990 to Sep 28th 1990. Ceased 24 hr operations because of acquisition problems experienced by some 8970 receivers. One hour on-air testing from Oct 3rd – Oct 29th . Resumed 24 hour operations Oct 30th, 1991 till Dec 24th 1990. |
Operational date: | 9610 Dec 25th 1990 for M-W, M-X, M-Y, M-Z Jan 17th 1991 for M-V 8970Z - Dec 25th 1990 |
Operations Ceased: | 8970 - 08 FEB 2010 9610 - 08 FEB 2010 |
Station Operation: | LORAN C: 8970 – SECONDARY 9610 - MASTER |
Station pair: | 8970 - BAUDETTE, DANA, MALONE, SENECA 9610 - GILLETTE, GRANGEVILLE, LAS CRUCES, RAYMONDVILLE, SEARCHLIGHT |
Loran Rate: | 9610 8970 |
On-Air: | 8970-Z 30 Oct 1990 9610-M early Aug 1990 |
Off-Air | 8970Z - 082000Z FEB 2010 -TERMINATION U.S. LORAN C OPS 9610M - 082000Z FEB 2010 - TERMINATION U.S. LORAN C OPS |
Monitor Rate: | |
Equipment: | AN/FPN-65A Timers AN/FSN-2(v) AN/FPN-64(v)-4 Solid State Transmitter 700ft Tower with 800 ft TLE |
Personnel Allowance: | ETC (OinC), ET1 (XPO), MK1 (EPO), and ET2 (OPS). |
Miscellaneous: | |
Commanding Officers / Officers in Charge |
PRECOM OINC: ETC Joe Jester, 01 JUL 1990 - 08 NOV 1990 OINC: ETC Joe Jester, 08 NOV 1990 – 01 SEP 1994 OINC: ETCS Thomas Lowrimore 01 SEP 1994 - 1999 OINC: ETC Robert Buxman MAR 1999 - MAY 2000 OINC: ETC Daniel Heineck 2000-2001 OINC: ETC John Hill 2001 - OINC: ETC Mark O'Heir 2006 Last OINC: ETC Shawn Ferguson OCT 2008 - FEB 2010 |
Pictures
"Commissioning Day
November 8, 1990"
" "
""Attention to Colors" Commissioning Day at
Boise City.
-- Photo provided by Joe Jester"
""Admiral, Loran Station Boise City is ready to
carry out it's mission"
states CPO Jester at the Commissioning Ceremony
-- Photo provided by Joe Jester"
"PO2 Barry Boyd (Ops PO) illustrates the loran
pulse to the guests at the Commissioning Ceremony
-- Photo provided by Joe Jester"
"Engine Room circa early 1990s
-- Photo provided by Joe Jester"
"Looking down from the top of the 700 foot
tower.
-- Photo provided by Joe Jester"
""Don't give me that look Rodney, you
volunteered to be a tower climber"
-- Photo provided by Joe Jester"
"Operations Room circa 1990s
-- Photo provided by Joe Jester"
"Security patrol on maneuvers. Just
kidding. :)
-- Photo provided by Joe Jester"
"View from Texline Road
-- Photo provided by Joe Jester"
1992 Christmas Card
Citation: